CIPAA, LAD and EOT: construction contract guidance for Malaysia
Most contract problems on site come down to three questions: when do I get paid, who carries the delay, and what does it cost me. This guide sets out the basics of CIPAA, extension of time and liquidated damages, and how Caprix Advise helps you understand where you stand.
Advise is included on Pro and Max · Guidance, not legal advice
CIPAA: getting paid
The Construction Industry Payment and Adjudication Act 2012 (CIPAA), in force since 15 April 2014, gives parties to a written construction contract a fast statutory route to resolve payment disputes. An adjudicator decides the dispute within a fixed timetable, and the decision binds the parties unless it is set aside or the dispute is finally settled by arbitration or the court.
The process runs on short deadlines counted in working days:
| Step | Time limit under the Act |
|---|---|
| Payment claim served by the unpaid party | Starts the process |
| Payment response from the other party | Within 10 working days of the payment claim |
| Adjudication claim | Within 10 working days of the adjudicator accepting the appointment |
| Adjudication response | Within 10 working days of the adjudication claim |
| Adjudication reply | Within 5 working days of the adjudication response |
| Adjudicator's decision | Within 45 working days of the response or reply |
This is a summary to show the shape of the process. Read the Act itself, and take advice, before you act on a deadline.
Extension of time: who carries the delay
When completion is delayed by something the contractor is not responsible for, the contract usually allows the completion date to be extended. Whether a claim succeeds often turns less on the delay itself than on the paperwork: whether notice was given, in the form and within the time the contract requires.
The standard forms used in Malaysia, including PAM, PWD 203A, CIDB, IEM and FIDIC, each have their own notice requirements and time bars. Know which form you are on, and keep dated records from the day an event starts.
Liquidated damages: what delay costs
Liquidated damages, often called LAD, are a sum agreed in the contract for each day or week that completion is late. They are meant to fix the employer's loss in advance, so it does not have to be argued afterwards.
Whether and how much can be recovered depends on the clause, on whether time was properly extended, and on how Malaysian courts have applied the Contracts Act 1950 to such clauses. This is an area where the case law matters, and where the facts of your project decide the answer.
How Caprix Advise helps
Ask in plain language
Describe what is happening and what you want to know. Set your role, the contract form, the issue and the state the site is in.
Deadlines from a key date
Give a key date and Advise works out the deadlines that follow from it, counting working days and public holidays for that state.
Your own documents
Attach the clauses, letters, notices or certificates the question turns on: up to 5 PDFs per chat, of up to 150 pages each. Scanned PDFs work too.
A library of Malaysian cases
Browse construction judgments by topic and court for free. Opening a case, with what the court held and commentary, costs 1 credit, charged once.
Advise covers payment and claims, delay and extension of time, liquidated damages, variations, termination, CIPAA adjudication, arbitration, time bars, certificates, bonds and defects.
Your documents stay private
Only the extracted text of an attached document is kept; scanned images are not stored. It is used solely to answer your questions in that chat, is never used to train AI models, and is deleted after 30 days. You can remove a file at any time.
Guidance, not legal advice
Advise helps you understand your position and the relevant cases, but it can make mistakes and it does not know every fact of your project. Before issuing a notice, withholding payment, starting adjudication or arbitration, or terminating, consult an advocate and solicitor or a contracts specialist.
A question costs 5 credits, and each PDF you attach costs 5. Free gives 50 credits every month. Pro is RM99 a month with 2,000 credits, and Max is RM149 a month with 4,000. See the full plan comparison →
Questions about CIPAA, LAD and EOT
What is CIPAA?
How long does a party have to respond to a CIPAA payment claim?
Can Caprix work out my contract deadlines?
Which contract forms does Advise understand?
Is Advise a substitute for a lawyer?
What does Advise cost?
Know where you stand before you write the letter
Start free with 50 credits every month. No credit card needed.
Get started free Variation orders →