CIPAA, LAD and EOT: construction contract guidance for Malaysia

Most contract problems on site come down to three questions: when do I get paid, who carries the delay, and what does it cost me. This guide sets out the basics of CIPAA, extension of time and liquidated damages, and how Caprix Advise helps you understand where you stand.

Advise is included on Pro and Max · Guidance, not legal advice

CIPAA: getting paid

The Construction Industry Payment and Adjudication Act 2012 (CIPAA), in force since 15 April 2014, gives parties to a written construction contract a fast statutory route to resolve payment disputes. An adjudicator decides the dispute within a fixed timetable, and the decision binds the parties unless it is set aside or the dispute is finally settled by arbitration or the court.

The process runs on short deadlines counted in working days:

StepTime limit under the Act
Payment claim served by the unpaid partyStarts the process
Payment response from the other partyWithin 10 working days of the payment claim
Adjudication claimWithin 10 working days of the adjudicator accepting the appointment
Adjudication responseWithin 10 working days of the adjudication claim
Adjudication replyWithin 5 working days of the adjudication response
Adjudicator's decisionWithin 45 working days of the response or reply

This is a summary to show the shape of the process. Read the Act itself, and take advice, before you act on a deadline.

Extension of time: who carries the delay

When completion is delayed by something the contractor is not responsible for, the contract usually allows the completion date to be extended. Whether a claim succeeds often turns less on the delay itself than on the paperwork: whether notice was given, in the form and within the time the contract requires.

The standard forms used in Malaysia, including PAM, PWD 203A, CIDB, IEM and FIDIC, each have their own notice requirements and time bars. Know which form you are on, and keep dated records from the day an event starts.

Liquidated damages: what delay costs

Liquidated damages, often called LAD, are a sum agreed in the contract for each day or week that completion is late. They are meant to fix the employer's loss in advance, so it does not have to be argued afterwards.

Whether and how much can be recovered depends on the clause, on whether time was properly extended, and on how Malaysian courts have applied the Contracts Act 1950 to such clauses. This is an area where the case law matters, and where the facts of your project decide the answer.

How Caprix Advise helps

Ask in plain language

Describe what is happening and what you want to know. Set your role, the contract form, the issue and the state the site is in.

Deadlines from a key date

Give a key date and Advise works out the deadlines that follow from it, counting working days and public holidays for that state.

Your own documents

Attach the clauses, letters, notices or certificates the question turns on: up to 5 PDFs per chat, of up to 150 pages each. Scanned PDFs work too.

A library of Malaysian cases

Browse construction judgments by topic and court for free. Opening a case, with what the court held and commentary, costs 1 credit, charged once.

Advise covers payment and claims, delay and extension of time, liquidated damages, variations, termination, CIPAA adjudication, arbitration, time bars, certificates, bonds and defects.

Your documents stay private

Only the extracted text of an attached document is kept; scanned images are not stored. It is used solely to answer your questions in that chat, is never used to train AI models, and is deleted after 30 days. You can remove a file at any time.

Guidance, not legal advice

Advise helps you understand your position and the relevant cases, but it can make mistakes and it does not know every fact of your project. Before issuing a notice, withholding payment, starting adjudication or arbitration, or terminating, consult an advocate and solicitor or a contracts specialist.

A question costs 5 credits, and each PDF you attach costs 5. Free gives 50 credits every month. Pro is RM99 a month with 2,000 credits, and Max is RM149 a month with 4,000. See the full plan comparison →

Questions about CIPAA, LAD and EOT

What is CIPAA?
CIPAA is the Construction Industry Payment and Adjudication Act 2012, in force since 15 April 2014. It gives parties to a written construction contract a statutory adjudication process for payment disputes, run to a fixed timetable.
How long does a party have to respond to a CIPAA payment claim?
A payment response is due within 10 working days of receiving the payment claim. Later steps have their own limits, including 10 working days for the adjudication claim and the adjudication response, and 45 working days for the adjudicator's decision. Check the Act before relying on any deadline.
Can Caprix work out my contract deadlines?
Yes. Give Advise a key date and the state the site is in, and it works out the deadlines that follow, counting working days and public holidays for that state. Treat the result as guidance and confirm it before you act.
Which contract forms does Advise understand?
You can set the contract form when you ask, including PAM, PWD 203A, CIDB, IEM and FIDIC, among others. You can also attach the actual clauses as a PDF so the answer is based on your contract's wording.
Is Advise a substitute for a lawyer?
No. Advise gives guidance to help you understand your position and the relevant Malaysian cases. It can make mistakes and does not know every fact of your project. Consult an advocate and solicitor or a contracts specialist before taking a formal step.
What does Advise cost?
A question costs 5 credits and each attached PDF costs 5. Browsing the case library is free, and opening a case costs 1 credit, charged once. Advise is available on Pro and Max.

Know where you stand before you write the letter

Start free with 50 credits every month. No credit card needed.

Get started free Variation orders →